If Mayor Richard M. Daley can’t get his phantasmagoric O’Hare Airport expansion plan completed in time for the 2016 Olympics, maybe he can get the Games postponed.
That’s because he has a better chance of getting the Olympics delayed than he has of realizing his airport expansion hallucination by then.
Doubt that? Then consider the Daley airport record so far: False starts, delays, broken promises, excuses. After huge cost overruns and missed timetables for just the first, northern runway (still not open) of the expansion plan’s Phase 1, the news out of City Hall is that Daley has ordered that $200 million more be spent on what only can be called the premature planning and engineering of the even more difficult Phase 2. That’s even though the financially troubled airlines that are supposed to pay for much of the entire expansion have said they are not in for phase 2.Read more at the Chicago Daily Observer